Scaled Agile Framework (SAFe) is an approach to software development that aims to help organizations deliver high-quality software faster and more efficiently. SAFe is designed to help teams of teams, working across different departments and locations, to collaborate effectively and achieve their goals. The SAFe framework has become increasingly popular in recent years, and many organizations are looking for certified SAFe professionals to help them implement the framework. One of the key roles in the SAFe framework is the Release Train Engineer (RTE).
NEW QUESTION # 59
What is the Scrum Master's role in team breakout #1?
- A. Create mitigation plans for each risk
- B. Raise team level risks
- C. Facilitate the coordination with other teams for dependencies
- D. Resolve dependencies with other teams
Answer: C
NEW QUESTION # 60
What is included in the Inspect and Adapt agenda?
- A. System Demo
- B. Program backlog refinement
- C. Quantitative and qualitative measurement
Answer: C
NEW QUESTION # 61
How does SAFe handle the 'fear of conflict' team dysfunction?
- A. Reviews results at the end of every iteration
- B. Has teams engage in retrospectives
- C. Avoids discussion of disagreements
- D. Uses scrum to create a safe environment for conflict
Answer: D
NEW QUESTION # 62
What is the most accurate definition of DevOps?
- A. A process that provides visibility to impediments between writing code and deliv-ering value
- B. A mindset, culture, and set of technical practices that emphasizes close coopera-tion to provide value to the Customer
- C. A set of tools and processes that govern how code is deployed
- D. A method that ensures Operations works with Development every day to deliver value
Answer: B
NEW QUESTION # 63
Which statement is true about the SAFe backlog model?
- A. Stories are in the Solution Backlog
- B. Capabilities are in the Program Backlog
- C. Features are in the Program Backlog
Answer: A
NEW QUESTION # 64
Product Management is responsible for which activity?
- A. Establishing an architectural vision for the Agile Release Release Train
- B. Defining Program Backlog content
- C. Prioritizing the Portfolio Backlog
Answer: B
NEW QUESTION # 65
Why would a Release Train Engineer use an Iteration and Program Increment Calendar?
- A. To know the cycle time between important team and train events
- B. To visualize the Agile Release Train's cadence and synchronization
- C. To ensure that key ceremonies don't conflict with non-SAFe ceremonies
- D. To create a BVIR of the important team and ART milestones
Answer: B
NEW QUESTION # 66
Why is the innovation pillar of the House of Lean important to SAFe?
- A. It provides the shortest sustainable lead time
- B. It avoids the start-stop-start of project delays
- C. It ensures delivery of valuable products
- D. It is the foundation of the House of Lean
Answer: C
NEW QUESTION # 67
In the SAFe work item hierarchy, Features are decomposed into what?
- A. Stories
- B. Sub-Tasks
- C. Tasks
- D. Capabilities
Answer: A
NEW QUESTION # 68
Why is the problem-solving workshop more effective than traditional lessons learned documents?
- A. Collaboration over documentation is a key recommendation of the Agile Manifes-to
- B. It makes improvements actionable through backlog items for the next Program Increment
- C. Workshops are more engaging than document writing
Answer: B
NEW QUESTION # 69
What can occur as a result of not having an Innovation and Planning Iteration?
- A. Technical debt can grow uncontrollably
- B. Delivery can be stifled incrementally
- C. Bottlenecks can be hard to identify and resolve
- D. Teams can have no time for fixing bugs
Answer: A
NEW QUESTION # 70
What is one way Kanbans are used in SAFe?
- A. To manage Program Increment (Pl) Objectives
- B. To manage runway cadence
- C. To manage queue length
Answer: C
NEW QUESTION # 71
Several Scrum Masters seem to be deadlocked in a disagreement on what to do about a shared issue. What is an appropriate coaching technique for the RTE to use?
- A. Asking powerful questions to invite creativity and new possibilities
- B. Being the final "decision making authority" once all views have been heard
- C. Driving an empirical assessment of the problem using metrics
- D. Bringing fresh emphasis to lean-agile's respect for people and culture
Answer: A
NEW QUESTION # 72
In addition to Innovation and Planning, what else does the IP Iteration provide time for?
- A. Additional planned work
- B. An opportunity to integrate and perform end-to-end testing
- C. Building in quality and compliance
- D. An estimating guard band
Answer: D
NEW QUESTION # 73
What is the best way for the Release Train Engineer to show progress of work in the cur-rent Program Increment (PI) to management?
- A. Conduct a System Demo
- B. Generate a velocity trend report
- C. Arrange for a separate meeting with Business Owners
- D. Conduct a retrospective
Answer: A
NEW QUESTION # 74
What is a characteristic of an effective Scrum Master?
- A. As a technical expert
- B. Removes all conflict
- C. Gives open, honest opinions
- D. Understands customer needs
Answer: A
NEW QUESTION # 75
......
The SAFe-RTE exam is an important certification for individuals who are looking to advance their career in Agile and SAFe. SAFe Release Train Engineer certification demonstrates that an individual has the knowledge and skills needed to effectively manage and coordinate the activities of the Agile Release Train. SAFe Release Train Engineer certification is recognized by organizations around the world and can help individuals stand out in a competitive job market.