Valid AgilePM-Practitioner Test Answers & APMG-International AgilePM-Practitioner Exam PDF [Q16-Q35]

Share

Valid AgilePM-Practitioner Test Answers & APMG-International AgilePM-Practitioner Exam PDF

APMG-International AgilePM-Practitioner Certification Real 2025 Mock Exam

NEW QUESTION # 16
How should the Project Manager encourage the contractors to turn up on time?

  • A. Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.
  • B. Encourage open and honest communication to re-establish an environment of trust.
  • C. Place a penalty clause on all contractors for late arrival.
  • D. Appoint Team Leaders to each of the electrical and plumbing teams.

Answer: B


NEW QUESTION # 17
Column 1 is a list of individuals from within the Xan Insurance Company and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project Management team role they are fulfilling. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
* Business Sponsor
* Business Analyst
* Business Ambassador
* Business Advisor
* Solution Developer
* Technical Coordinator
* DSDM Coach
* Project Manager

Answer:

Explanation:

Explanation:
Based on the Agile Project Management roles and the responsibilities outlined for each individual in the XAN Insurance Company Web Project scenario, the following selections can be made:
* Manager of Web & Digital Media - will oversee and report progress on the delivery of the overall system.Selection: H. Project ManagerExplanation: The Manager of Web & Digital Media's role of overseeing and reporting on the project's progress aligns with the responsibilities of a Project Manager in an Agile setting, who is responsible for ensuring that the project meets its objectives and is delivered on time.
* Finance Director - has budgetary control and will release finance for the project subject to expected benefits.Selection: A. Business SponsorExplanation: The Finance Director's control over the budget and the decision to release funds based on the expected benefits align with the role of a Business Sponsor, who is typically responsible for the project's budget and ensuring that it delivers value to the business.
* Sales Manager - will formulate design options for new business processes that do not adversely affect business as usual.Selection: B. Business AnalystExplanation: The Sales Manager's responsibility for formulating design options for new business processes mirrors the role of a Business Analyst in Agile Project Management, who works to understand the business needs, assess the impact of changes, and ensure the solution meets business requirements.
* Operations Manager - oversees the design and integrity of the technical aspects of the solution.
Selection: F. Technical CoordinatorExplanation: The Operations Manager's focus on the technical design and integrity of the solution corresponds to the role of a Technical Coordinator in Agile projects, who ensures that the technical aspects of the project align with the business needs and technical standards.


NEW QUESTION # 18
What action should the Project Manager take during the Close-Out of Timebox C?

  • A. Ensure that lessons are learned so that similar issues do not occur in future Timeboxes.
  • B. Carry out final checks to ensure the deliverables of Timebox C meet the expected standards.
  • C. Initiate the work required to complete the windows to the required standard.
  • D. Remove 'Aspects' from the supplier list for all future projects.

Answer: B


NEW QUESTION # 19
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?

  • A. The Project Manager should move a Must Have requirement from Timebox B into Timebox C.
  • B. The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.
  • C. The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List.
  • D. The Project Manager should extend the timescale of Timebox B and shorten Timebox C.

Answer: B

Explanation:
C: The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.
Rationale:
In Agile Project Management, priorities are often reassessed and reprioritized based on new information or changes in the project's context. The need for a secondary exit due to compliance with fire safety regulations would necessitate such a reassessment. The Business Visionary and Business Sponsor, who provide the vision and funding for the project, together with the Solution Development Team, who are responsible for implementing solutions, should collaboratively review the Prioritised Requirements List to reflect this new priority. This change must be agreed upon by these key stakeholders to ensure that it aligns with the business needs and project goals.


NEW QUESTION # 20
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying controls to the end of Development Timebox C.
What action should the Project Manager take when considering the End of Timebox Review?

  • A. Encourage the Marketing Director to attend the End of Timebox Review.
  • B. Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.
  • C. Attend the next Daily Stand-up to raise an issue about the windows.
  • D. Prepare a summary of progress against plan, for presentation at the review.

Answer: D


NEW QUESTION # 21
Which 2 statements explain why the Architecture Angels' Operations Director would be an appropriate Business Advisor?

  • A. Has been involved with monitoring the progress of previous company projects.
  • B. Has specialist knowledge about the targets for staff performance.
  • C. Is one of the original four founders of the company.
  • D. Is in charge of providing appropriate scenarios to check the security systems.
  • E. Can provide input about problems experienced by the people who run the hotels.

Answer: D,E


NEW QUESTION # 22
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the agreement of the team.
Which Agile principle MOST influences this course of action?

  • A. Develop iteratively.
  • B. Deliver on time.
  • C. Never compromise quality.
  • D. Build incrementally from firm foundations.

Answer: B


NEW QUESTION # 23
Which 2 statements represent appropriate entries for the Development
Approach Definition?

  • A. Once deployed, the number of policies sold through traditional telephone sales will be compared with the number of sales processed online through the website.
  • B. Accessibility and performance of the new online quotation area is to be tested using a tool called Sitebeam.
  • C. The Finance Director has requested a detailed report be produced after 12 weeks, showing costs to date and forecast cost to complete.
  • D. An easy to use web development tool called 'WebMatrix' is to be used to develop and maintain the website extension.
  • E. The Sales Manager will introduce an awards or bonus scheme, designed to create competition between the sales assistants.

Answer: B,D

Explanation:
For the XAN Insurance Company Web Project, the Development Approach Definition document should outline the methodologies, tools, and techniques to be used during the development process of the project. It focuses on how the project will be executed in terms of technical and management practices.
Selected Statements for the Development Approach Definition:
C: An easy to use web development tool called 'WebMatrix' is to be used to develop and maintain the website extension.
E: Accessibility and performance of the new online quotation area is to be tested using a tool called Sitebeam.
C: This statement directly specifies a tool (WebMatrix) that will be used for web development and maintenance in the project. It is a clear choice regarding the technical approach and infrastructure, making it suitable for inclusion in the Development Approach Definition.
E: Mentioning Sitebeam as a tool for testing accessibility and performance outlines specific methods for ensuring quality and usability in the development process. It provides actionable information on how testing will be conducted, fitting the criteria for the Development Approach Definition.
Why Other Statements Are Excluded:
A: Introducing an awards or bonus scheme to create competition among sales assistants pertains more to internal sales team management and motivation strategies rather than the technical or methodological approach to developing the project.
B: Comparing traditional telephone sales with online sales is related to the project's performance measurement and post-implementation review, not the development approach or methodology used during the project.
D; The request from the Finance Director for a detailed cost report is related to project financial management and monitoring. While important, it does not detail the technical or methodological approach to developing the project's deliverables.


NEW QUESTION # 24
Which 2 actions should the Workshop Facilitator take to implement the new Must Have requirement?

  • A. Consolidate and circulate an agenda for the workshop.
  • B. Send a company-wide communication to explain the implications of the business change to all interested parties.
  • C. Assess the impact of the additional development costs on the original Business Case.
  • D. Add the tasks required to develop the new financial transaction
    functionality to the Delivery Plan.
  • E. Encourage all parties to contribute, irrespective of their views.

Answer: A,E


NEW QUESTION # 25
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?

  • A. Prepare a report describing the outcome of the workshop.
  • B. Agree to disagree, and close the workshop acknowledging that all participants are entitled to their own view.
  • C. Present own interpretation of what the system should include.
  • D. Present the group with a predefined specification of what should be included.
  • E. Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.

Answer: A,E

Explanation:
The two actions that the Workshop Facilitator should take if the team cannot agree on the system content are:
* C. Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue. This will ensure that the disagreement does not stall the project and that there is a clear plan for how to move forward.
* E. Prepare a report describing the outcome of the workshop. This will provide a record of the discussion and any decisions made, which can be useful for future reference and for keeping stakeholders informed.
Please note that while presenting their own interpretation of what the system should include (option A) or presenting the group with a predefined specification of what should be included (option B) might seem like potential solutions, these actions could bias the discussion and may not lead to a solution that meets all stakeholders' needs. Agreeing to disagree and closing the workshop (option D) could leave the issue unresolved, which could cause problems later in the project. The facilitator's role is to guide the discussion and help the team reach a consensus, not to impose their own views or prematurely end the discussion.


NEW QUESTION # 26
Which 2 statements represent appropriate entries for the plan for Post-Project activities?

  • A. A report showing the number of application forms completed online
    through the website for coffee shop insurance policies will be produced weekly.
  • B. The Sales Manager will create a company-wide email showing the
    number of policies sold weekly by each of the sales assistants.
  • C. Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
  • D. Before the product is deployed, the Sales Manager will circulate a copy of the revised sales procedure for processing coffee shop insurance sales.
  • E. The Project Manager will attend Daily Stand-up meetings to observe
    progress.

Answer: A,C

Explanation:
For the XAN Insurance Company Web Project, the plan for Post-Project activities should include actions and measures that will be undertaken after the project's deliverables have been implemented to ensure sustained benefits, monitor performance, and facilitate continuous improvement.
Selected Statements for the Plan for Post-Project Activities:
D: A report showing the number of application forms completed online through the website for coffee shop insurance policies will be produced weekly.
E: Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
D: Producing a weekly report on the number of application forms completed online is a clear post-project activity. It provides ongoing monitoring of the project's impact and the effectiveness of the online system in attracting coffee shop insurance policies.
E; Comparing the processing times of online sales to telephone sales after the new system's deployment is an essential post-project activity. It evaluates the efficiency and effectiveness of the new online system, offering insights into improvements and adjustments that may be needed.
Why Other Statements Are Excluded:
A: Creating a company-wide email to show the number of policies sold by each sales assistant weekly is more related to internal sales performance monitoring and motivation rather than a specific post-project activity tied to the project's objectives.
B: Circulating a copy of the revised sales procedure before product deployment is a preparation step for the transition to the new system, rather than a post-project activity.
C: The Project Manager attending Daily Stand-up meetings is part of the ongoing project management and team coordination activities during the project, not a post-project activity.
Topic 2, Hoy Hall Hotel Refurbishment Project
Scenario:
Hoy Hall Hotel Refurbishment Project
(Note:
Hoy Hall, a historic, timber-framed building dating from the 17th century, was originally the residence of the Lords of the Manor of Hoytown. The building is registered as a Heritage Building of Special Interest and is subject to restrictions in terms of development. Used as a hotel for over a century, it has recently fallen into disrepair, and for two years it has been completely unused, accelerating its deterioration. The local community has formed the Action Group "Hoy for Hoy Hall" to save the building, and wants to be closely involved in its future success.
After much discussion Hoy Hall has been purchased by Architecture Angels (AA), a small company whose directors are experienced hoteliers. Five years ago they decided to move into the property renovation business and have recently restored two other similarly-endangered buildings for use as hotels.
Architecture Angels are keen to both support local businesses and to have local people run their hotels, giving them a significant amount of autonomy to do this.
To maintain core consistency, the hotels use Architecture Angels' Head Office services, such as IT operations, accounting, payroll, stocktaking, compliance, human resources and property management. The Head Office is based 80 miles from Hoy Hall.
Recently Architecture Angels commenced an Agile project to renovate Hoy Hall, which has a large downstairs hall and reception area, and 20 potential bedrooms upstairs. The roof requires extensive repairs and the electrical and plumbing installations require complete replacement. The 40 acres of land around the site are overgrown and need to be restored, and the driveway needs re-laying.
In the hotel industry, the trend for direct customer bookings via the internet has had a major impact on the growth of those hotels with this facility. Online booking now accounts for around 80% of room bookings, with only 20% being made via walk-in and telephone enquiries. Before Hoy Hall can open for business, a reservation system must be fully operational.
Architecture Angels use contractors to manage such work and have good
relationships with two local companies: Timber Tigers (TT) who will handle the internal works, and Earth Excavations (EE) who will handle the gardens.
A Project Manager, who has since left the company, started the Feasibility phase. This phase has been continued by the Senior Management Team, which consists of the Sales, Marketing, and Finance Directors and the Chief Executive.
This was scheduled to take a month and has almost been completed. A
Feasibility Assessment has been produced. An Outline Business Case has been completed which assessed the project as being viable.
The Architecture Angels Senior Management Team will be responsible for
Steering the project.
The table below shows the appointments planned for the project team and is subject to change.

Additional Information:
The project is approaching the end of Feasibility. The original Project Manager was involved in drafting a Delivery Plan for the project but not in the outline refurbishment options.
The Senior Management Team generated several options for the refurbishment.
All the options included a landscaping solution for the gardens and re-laying of the driveway, as the solution will not be acceptable without these. However, the best solution for the refurbishment is still under debate. The new Project Manager has suggested that a Feasibility Prototype could consist of paper-based drawings for each option. The "Hoy for Hoy Hall" Action Group thinks that a physically-built representation is mandatory for a prototype and wants a small-scale model of the recommendation for the building. The time available to produce this, however, is limited.
Contracts for resources have not yet been signed and will be postponed until the chosen outline solution has been agreed.


NEW QUESTION # 27
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
When specifying high-level prioritised requirements during Foundations, the Business Visionary has suggested that acceptance criteria for the requirement to "temporarily weatherproof the roof" should NOT be set until Solution Development Timebox A.
Is this an appropriate approach to setting high-level acceptance criteria?

  • A. No, because by the end of Foundations the quality expectations and overall acceptance criteria for at least the first increment should have been set, and high-level acceptance criteria set for later increments.
  • B. Yes, because the Local Planning Authority Officer will set the acceptance criteria.
  • C. No, because a Review Session should have been scheduled during Feasibility to enable the Solution Development Team to validate their understanding of the Local Planning Authority Officer's expectations.
  • D. Yes, because acceptance criteria are NOT set before the Timeboxed work is started.

Answer: A

Explanation:
C: No, because by the end of Foundations the quality expectations and overall acceptance criteria for at least the first increment should have been set, and high-level acceptance criteria set for later increments.
Rationale:
In Agile Project Management, it's important to establish high-level acceptance criteria early in the project to guide development and ensure that the solution meets the business needs and quality expectations. The Foundations phase is when the project's scope, objectives, and methods are defined, including the acceptance criteria for the first increment and at a high level for subsequent increments. This ensures that everyone has a clear understanding of what "done" looks like before development begins, reducing the risk of misalignment and rework.


NEW QUESTION # 28
Resources are limited. The Sales Manager has two marketing assistants who may be able to give a few hours a week between them to the project.
What action should the Project Manager take?

  • A. Accept that members of the Solution Development Team will be
    inconsistent.
  • B. Try to secure formal agreement as to how many hours per week the
    marketing assistants will spend on the project.
  • C. Make each Timebox as long as possible to ensure the marketing
    assistants have enough time to complete any work allocated to them
    within the boundaries of the Timebox.
  • D. Schedule the two marketing assistants to work at different times so they can hand matters over to one another.

Answer: B

Explanation:
In the context of Agile Project Management, it is crucial to have clear commitments regarding team members' availability to ensure that project planning and execution can be as accurate and effective as possible. By securing a formal agreement on the hours the marketing assistants can dedicate to the project each week, the Project Manager can better plan tasks and allocate resources, thereby optimizing the team's capacity and ensuring that project timelines and deliverables are realistic and achievable.
References:
The Agile Project Management (AgilePM) framework emphasizes the importance of clear communication, resource planning, and commitment from all team members to ensure project success. Having a formal agreement on availability helps in setting clear expectations and allows for more effective planning and utilization of resources within the constraints of the project, aligning with Agile principles of collaboration, adaptability, and iterative progress.


NEW QUESTION # 29
The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.
At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.
However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of storage space on the company server and require minimal maintenance.
The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.
Remember to limit your answers to the number of selections requested in each question.
Which 2 individuals should the Facilitator invite to participate in the Workshop?

  • A. Representative for Timber Tigers (Solution Developer)
  • B. Chief Executive (Steering Group)
  • C. IT Operations Manager (Solution Development Team)
  • D. Representative for Earth Excavations (Solution Developer)
  • E. Marketing Director (Business Visionary)

Answer: C,E

Explanation:
The Facilitator should invite the following two individuals to participate in the Workshop:
D: IT Operations Manager (Solution Development Team) E. Marketing Director (Business Visionary) The rationale for this selection is that the disagreement is between the Marketing Director, who wants the reservation system to have professional photos and video tours (which impacts how the system will be used by potential customers and affects marketing strategy), and the IT Operations Manager, who is concerned with the system's technical limitations and maintenance. Both of these individuals are key to resolving the issue at hand, as they represent the conflicting requirements that need to be reconciled for the project to move forward.


NEW QUESTION # 30
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Feasibility Assessment?

  • A. The Architecture Angels' Finance Director should approve the final
    Business Case as part of the Feasibility Assessment.
  • B. The different options should be presented to the 'Hoy for Hoy Hall' Action Group for their feedback before the chosen outline solution is finalised.
  • C. The Timber Tigers' Site Manager should be the sole approver of the finalised Feasibility Assessment before development commences.
  • D. The new Project Manager should NOT be involved in finalising the
    Feasibility Assessment.
  • E. The Earth Excavations' Head Gardener should contribute to the outline solutions considered for the gardens.

Answer: A,B

Explanation:
In Agile Project Management, it's important to involve key stakeholders and to ensure that there's a collaborative approach to project decisions. Considering the Agile principles and the given scenario, the appropriate application of Agile to the Feasibility Assessment would likely involve the following statements:
B: The Architecture Angels' Finance Director should approve the final Business Case as part of the Feasibility Assessment. In Agile, it's crucial to ensure that the business aspect of any project aligns with the financial feasibility. The Finance Director's approval would be significant in validating the economic viability of the project.
D: The different options should be presented to the 'Hoy for Hoy Hall' Action Group for their feedback before the chosen outline solution is finalised. Agile encourages stakeholder engagement and iterative feedback.
Presenting options to the action group aligns with the Agile value of customer collaboration over contract negotiation, allowing for community input that could be vital due to the building's heritage status and the community's interest.


NEW QUESTION # 31
Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
Column 2:
A) Thought
B) Action
C) Conversation

Answer:

Explanation:

Explanation:
For each action in Column 1, here is the iterative development activity that the action represents from Column
2:
* The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
* B. Action
* The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
* A. Thought
* Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
* C. Conversation
* The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
* C. Conversation
* The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
* B. Action


NEW QUESTION # 32
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E. that applies. Each option can be used once, more than once or not at all.


Answer:

Explanation:

Explanation:
The activities from Column 1 should be performed in the following steps from Column 2, according to the iterative development process:
* Create the data entry screen for entering coffee bar details needed for a quotation.Selection: B.
ActionExplanation: Creating the data entry screen is part of the 'Action' step in iterative development, where the actual product or a part of it is being constructed.
* Enter numbers into a text-only field to see how the web page behaves.Selection: A. Thought Explanation: Testing how the web page behaves by entering data is part of the 'Thought' step, which includes reviewing and evaluating the work done, testing, and reflecting on the outcomes.
* Discuss the requirements of the new coffee bar insurance web page and agree which data fields are important.Selection: C. ConversationExplanation: Discussing and agreeing on the requirements is part of the 'Conversation' step, which involves interactions between team members and stakeholders to understand and define what needs to be built.


NEW QUESTION # 33
Using the additional information provided for this question in the Scenario Booklet, answer the following questions about the requirement for a fire exit from the upstairs of the building.
What is an appropriate reason to classify the need for a secondary exit from the upstairs of the building as a Must Have requirement?

  • A. Provision of a secondary exit from the upstairs of the building will ensure compliance with national fire safety regulations.
  • B. A secondary exit from the upstairs of the building would help ease congestion in busy periods during festivals.
  • C. A secondary exit from the upstairs of the building will provide a shorter and more direct route into the garden than the main stairway.
  • D. The requirement for a secondary exit from the upstairs of the building has to be made a higher priority in order to be moved to an earlier Timebox.

Answer: A

Explanation:
A: Provision of a secondary exit from the upstairs of the building will ensure compliance with national fire safety regulations.
Rationale:
Compliance with national fire safety regulations is non-negotiable and would be a legal requirement for the operation of the hotel. Therefore, any features required to meet these regulations would automatically be classified as "Must Have" due to their mandatory nature for safety and legal operation.


NEW QUESTION # 34
The Marketing Director has insisted that detailed requirements for the new coffee bar insurance web pages should be clearly defined in the early phases of the project.
What action should the Project Manager take?

  • A. Refuse to discuss any detailed requirements in the early phases.
  • B. Hold an early discussion to the level of detail necessary to establish a shared understanding of what is required.
  • C. Capture the Marketing Director's requirements in detail but leave the input of others until later in the project.
  • D. Agree to document the finite details of each requirement to ensure the web developers can accurately estimate the effort required to fulfil them.

Answer: B


NEW QUESTION # 35
......


APMG-International AgilePM-Practitioner Exam Syllabus Topics:

TopicDetails
Topic 1
  • People and Roles: In this section, the topics covered include various roles involved in an Agile project and how they relate to each other. The topics covered include the responsibilities of the Agile Project Manager, agile teams, and business owners.
Topic 2
  • Techniques: In this section, the topics covered various techniques that can be utilized including iterative development. Candidates are tested for their know-how of agile techniques and timeboxing.
Topic 3
  • Planning and Control: In this section, the exam covers planning and control of the project and vital concepts such as estimation and iterative strategy. It also covers how to utilize MoSCoW prioritization and mitigate any risks.
Topic 4
  • Lifecycle and Products: This section of the exam covers topics such as Agile project lifecycle, various stages of the lifecycle, agile products, Vision Documents, and Prototypes.

 

AgilePM-Practitioner Exam Questions and Valid AgilePM-Practitioner Dumps PDF: https://www.dumps4pdf.com/AgilePM-Practitioner-valid-braindumps.html

AgilePM-Practitioner Brain Dump: A Study Guide with Tips & Tricks for passing Exam: https://drive.google.com/open?id=1Og-wOpMrGvOQUDL20uMcXcOk0txG6tjg