NEW QUESTION 34
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.

  • A. The procurement type of the material must be internal.
  • B. The exact lot size procedure must be used.
  • C. The materials must allow sales order or project stock.
  • D. An MRP group must be assigned.

Answer: C,D

 

NEW QUESTION 35
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.

  • A. If the reduction strategy is set in each activity
  • B. If the reduction strategy is set in the network header
  • C. If the maximum reduction level is less than 100
  • D. If the appropriate reduction type is set in the parameters for network scheduling

Answer: B,D

 

NEW QUESTION 36
How can you grant individual authorization for WBS elements and networks?

  • A. Define a user status to lock the business transaction Update Project.
  • B. Set the system status to "Lock Master Data".
  • C. Activate access control lists (ACL) for the user master record.
  • D. Activate access control lists (ACL) for the project profile and the network profile.

Answer: D

 

NEW QUESTION 37
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.

  • A. For trend analysis
  • B. To start workflow tasks
  • C. To set an actual finish date for WBS elements
  • D. To transfer the actual date to the billing plan

Answer: A,D

 

NEW QUESTION 38
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.

  • A. Internal orders
  • B. Purchase order items
  • C. Sales order items
  • D. Reservations

Answer: B,D

 

NEW QUESTION 39
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?

  • A. Creation of purchase orders
  • B. Goods receipt for purchase orders
  • C. Calculation of actual values
  • D. Activity allocation

Answer: A

 

NEW QUESTION 40
You are working with networks and WBS elements. Which of the following statements applies?

  • A. You can reassign an activity from one network to another.
  • B. You have to maintain a network profile in the project profile.
  • C. You can assign the network header to multiple WBS elements.
  • D. You have to activate the operative indicator Account Assignment Element for WBS elements with activities.

Answer: A,C

 

NEW QUESTION 41
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.

  • A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".
  • B. You can only maintain the actual start of a WBS element if the finish date is not maintained.
  • C. You can always maintain the actual start and finish date of a WBS element.
  • D. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".

Answer: A,D

 

NEW QUESTION 42
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Company code
  • B. Sales organization
  • C. Operating concern
  • D. Plant
  • E. Controlling area

Answer: A,D,E

 

NEW QUESTION 43
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.

  • A. Profit center
  • B. Work
  • C. Activity type
  • D. Duration

Answer: B,C

 

NEW QUESTION 44
How can you confirm the working hours of different work centers for a single activity?

  • A. Enter direct activity allocation assigning multiple work centers.
  • B. Assign multiple work centers to the activity.
  • C. Enter multiple work centers within a single confirmation.
  • D. Create multiple confirmations for the activity and use the appropriate work center for each confirmation.

Answer: A

 

NEW QUESTION 45
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.

  • A. Material master
  • B. WBS element
  • C. BOM item
  • D. Network activity

Answer: C,D

 

NEW QUESTION 46
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

  • A. Activity
  • B. Milestone
  • C. Activity element
  • D. Network header

Answer: A

 

NEW QUESTION 47
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?

  • A. Availability control
  • B. Results analysis
  • C. Cost forecast
  • D. Easy Cost Planning

Answer: A

 

NEW QUESTION 48
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

  • A. The table of MRP controllers
  • B. The network profile
  • C. The scheduling parameters for the network
  • D. The control key

Answer: C

 

NEW QUESTION 49
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.

  • A. DIP is used to create a quotation.
  • B. Material determination is mandatory.
  • C. Sales prices are maintained in the DIP profile.
  • D. Usage of cost elements is mandatory.
  • E. Sources can be based on line items.

Answer: A,C,E

 

NEW QUESTION 50
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.

  • A. Planned dates
  • B. Forecast dates
  • C. Baseline dates
  • D. Basic dates

Answer: B,D

 

NEW QUESTION 51
What is the reason for assigning billing plans in customer projects?

  • A. Billing plans enable the billing process to be carried out.
  • B. Billing plans are used for revenue planning.
  • C. Billing plans are copied automatically to the sales order item.
  • D. Billing plans are prerequisites for quotation creation.

Answer: A

 

NEW QUESTION 52
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.

  • A. Relationships can be used to connect activities of different networks.
  • B. Material components can be assigned to activity elements.
  • C. A network can be activity-account-assigned and header-account-assigned.
  • D. A network activity can be assigned to several WBS elements.

Answer: A,C

 

NEW QUESTION 53
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.

  • A. Progress analysis
  • B. Results analysis
  • C. Settlement
  • D. Milestone trend analysis
  • E. Confirmations

Answer: A,B,C

 

NEW QUESTION 54
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Milestones
  • B. Project definition
  • C. Sales order items
  • D. WBS elements

Answer: C,D

 

NEW QUESTION 55
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

  • A. Network profile
  • B. Data entry profile
  • C. Network type
  • D. Project profile

Answer: B

 

NEW QUESTION 56
......