From whom does a Team Manager obtain approval for a completed product?

  • A. The authority defined in the Product Description
  • B. Senior Supplier
  • C. Project Support
  • D. Project Manager

Answer: A

 

NEW QUESTION 176
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

  • A. Themes
  • B. Principles
  • C. Techniques
  • D. Processes

Answer: B

Explanation:
Section: Volume A

 

NEW QUESTION 177
How should the Team Manager report that tolerances are forecast to be exceeded?

  • A. Create a Highlight Report
  • B. Raise an issue
  • C. Create an Exception Report
  • D. Grant a concession

Answer: B

 

NEW QUESTION 178
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

  • A. Risk
  • B. Unique
  • C. Cross-functional
  • D. Change

Answer: C

 

NEW QUESTION 179
Which is a purpose of the 'initiating a project' process?

  • A. To enable an organization to understand the work needed to deliver the project's products
  • B. To provide a fixed point at which acceptance for the project product is confirmed
  • C. To enable the project board to decide whether it is worthwhile to initiate a project
  • D. To produce a stage plan for each stage of a multi-stage project

Answer: C

Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Initiating_a_Project#Objective

 

NEW QUESTION 180
In which process is the work to be done assigned to a team manager?

  • A. Directing a project
  • B. Controlling a stage
  • C. Managing a stage boundary
  • D. Managing product delivery

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Controlling_a_Stage

 

NEW QUESTION 181
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

  • A. Quality Management Strategy
  • B. Follow-on action recommendations
  • C. Stage Plan
  • D. Communication Management Strategy

Answer: D

Explanation:
Section: Volume A

 

NEW QUESTION 182
How are team managers involved in tailoring PRINCE2 suit the project?

  • A. Team managers are accountable for the tailoring of the work packages
  • B. Team managers may advice on tailoring to improve the management of work packages
  • C. Team managers should document the tailoring of the work packages
  • D. Team managers should not be involved in tailoring PRINCE2

Answer: B

 

NEW QUESTION 183
Which is a responsibility of the project board?

  • A. To ensure production of the project's outputs
  • B. To implement the change control approach
  • C. To manage the team managers and project support
  • D. To ensure effective communication with external stakeholders

Answer: D

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Organization#Project_Board

 

NEW QUESTION 184
Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.

  • A. project approach appropriate for delivering a project is selected
  • B. aim is to establish sound foundations to achieve a successful project
  • C. minimum necessaryis done to decide if a project is worthwhile
  • D. Project Brief is assembled and approved

Answer: B

 

NEW QUESTION 185
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

  • A. products
  • B. project management team
  • C. controls
  • D. stages

Answer: A

 

NEW QUESTION 186
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

  • A. Project Plan
  • B. Team Plan
  • C. Benefits Review Plan
  • D. Stage Plan

Answer: D

 

NEW QUESTION 187
Which statement is true for ALL project stakeholders?

  • A. Review the Communication Management Strategy
  • B. Support the project
  • C. Internal to the corporate organization
  • D. May either affect or be affected by the project

Answer: D

 

NEW QUESTION 188
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.

  • A. decides who is responsible
  • B. has responsibility
  • C. and the project board are responsible
  • D. and the team manager(s) are accountable

Answer: B

Explanation:
Explanation
Reference http://prince2.wiki/Directing_a_Project

 

NEW QUESTION 189
Which is a key decision made during the 'directing a project' process?

  • A. Approve the project manager role description
  • B. Approve the proposed project mandate
  • C. Confirm that the benefits management approach addresses all expected benefits
  • D. Select and appoint the project executive

Answer: A

Explanation:
Explanation
Reference
https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project-process-in-princ

 

NEW QUESTION 190
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

  • A. Project product description
  • B. Project brief
  • C. Project initiation documentation
  • D. Project mandate

Answer: C

 

NEW QUESTION 191
Which is created during the Starting up a Project process?

  • A. Project management team role descriptions
  • B. Quality Register
  • C. Communication Management Strategy
  • D. Project mandate

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 192
In what process is the authorization to deliver the project's products given?

  • A. Initiating a Project
  • B. Managing a Stage Boundary
  • C. Directing a Project
  • D. Starting up a Project

Answer: C

 

NEW QUESTION 193
Identify the missing words in the following sentence. A Change Authority may be given a [?] to enable it to finance new requirements.

  • A. risk budget
  • B. cost tolerance
  • C. scope tolerance
  • D. change budget

Answer: D

 

NEW QUESTION 194
......

Penetration testers simulate PRINCE2Foundation exam: https://www.dumps4pdf.com/PRINCE2Foundation-valid-braindumps.html

Bestselling On-The-Job Reference Exam Questionshttps://drive.google.com/open?id=1QvfPKUfje7cqVFwwT9pOT8DhMzyNYalj