
Master 2021 Latest The Questions PRINCE2 Certification and Pass PRINCE2Foundation Real Exam!
Penetration testers simulate PRINCE2Foundation exam PDF
NEW QUESTION 175
From whom does a Team Manager obtain approval for a completed product?
- A. The authority defined in the Product Description
- B. Senior Supplier
- C. Project Support
- D. Project Manager
Answer: A
NEW QUESTION 176
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
- A. Themes
- B. Principles
- C. Techniques
- D. Processes
Answer: B
Explanation:
Section: Volume A
NEW QUESTION 177
How should the Team Manager report that tolerances are forecast to be exceeded?
- A. Create a Highlight Report
- B. Raise an issue
- C. Create an Exception Report
- D. Grant a concession
Answer: B
NEW QUESTION 178
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
- A. Risk
- B. Unique
- C. Cross-functional
- D. Change
Answer: C
NEW QUESTION 179
Which is a purpose of the 'initiating a project' process?
- A. To enable an organization to understand the work needed to deliver the project's products
- B. To provide a fixed point at which acceptance for the project product is confirmed
- C. To enable the project board to decide whether it is worthwhile to initiate a project
- D. To produce a stage plan for each stage of a multi-stage project
Answer: C
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Initiating_a_Project#Objective
NEW QUESTION 180
In which process is the work to be done assigned to a team manager?
- A. Directing a project
- B. Controlling a stage
- C. Managing a stage boundary
- D. Managing product delivery
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Controlling_a_Stage
NEW QUESTION 181
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
- A. Quality Management Strategy
- B. Follow-on action recommendations
- C. Stage Plan
- D. Communication Management Strategy
Answer: D
Explanation:
Section: Volume A
NEW QUESTION 182
How are team managers involved in tailoring PRINCE2 suit the project?
- A. Team managers are accountable for the tailoring of the work packages
- B. Team managers may advice on tailoring to improve the management of work packages
- C. Team managers should document the tailoring of the work packages
- D. Team managers should not be involved in tailoring PRINCE2
Answer: B
NEW QUESTION 183
Which is a responsibility of the project board?
- A. To ensure production of the project's outputs
- B. To implement the change control approach
- C. To manage the team managers and project support
- D. To ensure effective communication with external stakeholders
Answer: D
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Organization#Project_Board
NEW QUESTION 184
Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.
- A. project approach appropriate for delivering a project is selected
- B. aim is to establish sound foundations to achieve a successful project
- C. minimum necessaryis done to decide if a project is worthwhile
- D. Project Brief is assembled and approved
Answer: B
NEW QUESTION 185
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
- A. products
- B. project management team
- C. controls
- D. stages
Answer: A
NEW QUESTION 186
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
- A. Project Plan
- B. Team Plan
- C. Benefits Review Plan
- D. Stage Plan
Answer: D
NEW QUESTION 187
Which statement is true for ALL project stakeholders?
- A. Review the Communication Management Strategy
- B. Support the project
- C. Internal to the corporate organization
- D. May either affect or be affected by the project
Answer: D
NEW QUESTION 188
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
- A. decides who is responsible
- B. has responsibility
- C. and the project board are responsible
- D. and the team manager(s) are accountable
Answer: B
Explanation:
Explanation
Reference http://prince2.wiki/Directing_a_Project
NEW QUESTION 189
Which is a key decision made during the 'directing a project' process?
- A. Approve the project manager role description
- B. Approve the proposed project mandate
- C. Confirm that the benefits management approach addresses all expected benefits
- D. Select and appoint the project executive
Answer: A
Explanation:
Explanation
Reference
https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project-process-in-princ
NEW QUESTION 190
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
- A. Project product description
- B. Project brief
- C. Project initiation documentation
- D. Project mandate
Answer: C
NEW QUESTION 191
Which is created during the Starting up a Project process?
- A. Project management team role descriptions
- B. Quality Register
- C. Communication Management Strategy
- D. Project mandate
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 192
In what process is the authorization to deliver the project's products given?
- A. Initiating a Project
- B. Managing a Stage Boundary
- C. Directing a Project
- D. Starting up a Project
Answer: C
NEW QUESTION 193
Identify the missing words in the following sentence. A Change Authority may be given a [?] to enable it to finance new requirements.
- A. risk budget
- B. cost tolerance
- C. scope tolerance
- D. change budget
Answer: D
NEW QUESTION 194
......
Penetration testers simulate PRINCE2Foundation exam: https://www.dumps4pdf.com/PRINCE2Foundation-valid-braindumps.html
Bestselling On-The-Job Reference Exam Questions: https://drive.google.com/open?id=1QvfPKUfje7cqVFwwT9pOT8DhMzyNYalj