
View All C_TS422_2504 Actual Exam Questions, Answers and Explanations for Free
C_TS422_2504 Exam Free Practice Test with100% Accurate Answers
SAP C_TS422_2504 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
| Topic 7 |
|
| Topic 8 |
|
| Topic 9 |
|
NEW QUESTION # 51
What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.
- A. You can reschedule the operation using lead time scheduling.
- B. You can reschedule the operation using infinite scheduling in a planning table.
- C. You can reschedule the operation in the Manage Work Center Capacity app.
- D. You can reschedule the operation using finite scheduling in a planning table.
Answer: C,D
NEW QUESTION # 52
You are trying to create a production order and no valid production version can be selected. What could be the reasons?
Note: There are 2 correct answers to this question.
- A. The basic start date is NOT within the validity period of the production version.
- B. No bills of material (BOMs) are assigned to the production versions.
- C. No production lines are assigned to the production versions.
- D. The order lot size is NOT within the validity range of a production version.
Answer: A,D
NEW QUESTION # 53
You are a consultant on an SAP S/4HANA Cloud brownfield project. In a meeting the customer decides to remodel an existing business process in accordance with clean core principles.
Which of the following SAP Signavio solutions can be used for the remodeling?
- A. SAP Signavio Process Governance
- B. SAP Signavio Process Insights
- C. SAP Signavio Process Manager
- D. SAP Signavio Process Intelligence
Answer: A,C
NEW QUESTION # 54
Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?
- A. When several operations are maintained for one product
- B. When alternative resources are used within one operation
- C. When several production versions are maintained for one product
- D. When multiple planned orders are scheduled in parallel on one resource
Answer: B
NEW QUESTION # 55
In SAP documentation for MRP in Advanced Planning, you read that the MRP creates new planned orders through infinite scheduling. What does this mean for the capacity requirements of the new planned order?
- A. MRP creates the capacity requirements without considering existing load on the resources.
- B. MRP automatically assigns the capacity requirements after the last scheduled operation for each resource.
- C. MRP creates the capacity requirements on resources at the earliest possible production time.
- D. MRP automatically assigns the capacity requirements to resources with the earliest available capacity.
Answer: A
NEW QUESTION # 56
Which standard item categories can you select inside a bill of material (BOM)?
Note: There are 2 correct answers to this question.
- A. Class item
- B. Work item
- C. WBS item
- D. Non-plant item
Answer: A,D
NEW QUESTION # 57
What are the key features of using a low level code? Note: There are 2 correct answers to this question.
- A. To determine the priority of alternative components inside ATP
- B. To determine how costs are rolled up by product costing
- C. To determine the use of subitems inside material BOM (bill of material)
- D. To determine the sequence in which materials are planned in MRP
Answer: B,D
NEW QUESTION # 58
In the bucket planning mode of the capacity scheduling table, what happens if the sum of the requirements of all operations exceeds the available capacity of the bucket?
- A. The operation is rescheduled in the planning direction.
- B. The operation CANNOT be dispatched.
- C. The operation is rescheduled backwards.
- D. The operation is rescheduled to an alternative work center.
Answer: A
NEW QUESTION # 59
What is the difference between co-products and by-products?
Note: There are 2 correct answers to this question.
- A. Only co-products have movement type 101.
- B. Only co-products have movement type 531.
- C. Only co-products have a non-zero inventory valuation.
- D. Only co-products appear in the process or production order settlement rule.
Answer: A,C
NEW QUESTION # 60
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation? Note: There are 2 correct answers to this question.
- A. Scheduling of an operation takes place as close as possible to the desired date.
- B. Sequencing on multiactivity resources is automatically updated.
- C. Neighboring operations can be moved in both directions in order to create a slot.
- D. Changes are automatically implemented in the complete collective order.
Answer: A,D
NEW QUESTION # 61
Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
- A. Use a resource group.
- B. Use a planning group.
- C. Use a propagation range.
- D. Use a planning area.
Answer: A
NEW QUESTION # 62
Which of the following elements does MRP take into account during net requirement calculation?
Note: There are 2 correct answers to this question.
- A. ATP quantities
- B. Production orders
- C. Planned orders (firmed)
- D. Planned orders (unfirmed)
Answer: B,C
NEW QUESTION # 63
Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.
- A. Total replenishment lead time
- B. Setup time
- C. Opening period
- D. Float after production
Answer: B,D
NEW QUESTION # 64
Which alternative item strategies are available in bills of material (BOMs)?
Note: There are 2 correct answers to this question.
- A. Ranking
- B. Manual maintenance
- C. 100% check
- D. Simultaneous
Answer: B,C
NEW QUESTION # 65
You use planning strategy Finite Scheduling with Reverse want to allow scheduling in the past. How can you parameterize this in the strategy profile?
- A. Specify a negative planning horizon.
- B. Specify a negative offset time.
- C. Specify a negative opening period.
- D. Specify a negative PP/DS horizon.
Answer: B
NEW QUESTION # 66
Which business processes are affected by settings in the order type dependent parameters? Note: There are 2 correct answers to this question.
- A. Schedule production orders.
- B. Check material availability.
- C. Select master data.
- D. Define integration with cost accounting.
Answer: C,D
NEW QUESTION # 67
Which stard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. Work item
- B. Preliminary item
- C. Variablesize item
- D. WBS item
Answer: B,C
NEW QUESTION # 68
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
- A. Execute an infinite production planning run for the critical resources.
- B. Increase the capacity supply in a timephased interval.
- C. Form optimum sequences to reduce setup times.
- D. Reduce the planning time interval.
- E. Determine a time period with available capacity on the planning board.
Answer: B,C,E
NEW QUESTION # 69
What determines whether the planned independent requirements in dem management are consumed by other requirements? Note: There are 2 correct answers to this question.
- A. Requirements type
- B. Requirements profile
- C. Planning strategy
- D. Order type
Answer: A,C
NEW QUESTION # 70
......
C_TS422_2504 dumps Free Test Engine Verified By It Certified Experts: https://www.dumps4pdf.com/C_TS422_2504-valid-braindumps.html
Realistic C_TS422_2504 Accurate & Verified Answers As Experienced in the Actual Test!: https://drive.google.com/open?id=1eMDWK4t3VvchkQjrs4aepH46OgphX6tG